5. Design, launch, review and test are examples of which of the following work breakdown structure (WBS)
schemes?
A. Functions
B. Organizational units
C. Product components
D. Geographical areas
Answer: A
6. A project manager receives a request for a minor change to one of the deliverables. Which of the
following documents would MOST likely be impacted?
A. Work Breakdown Structure (WBS)
B. Project charter
C. Communication plan
D. Quality plan
Answer: A
7. Which of the following tools is the BEST to measure data organized in time sequence?
A. Run chart
B. Ishikawa diagram
C. Pareto chart
D. Histogram
Answer: A
Comments Feed: http://www.comptia-certification.com/feed.asp?q=comment&id=374
schemes?
A. Functions
B. Organizational units
C. Product components
D. Geographical areas
Answer: A
6. A project manager receives a request for a minor change to one of the deliverables. Which of the
following documents would MOST likely be impacted?
A. Work Breakdown Structure (WBS)
B. Project charter
C. Communication plan
D. Quality plan
Answer: A
7. Which of the following tools is the BEST to measure data organized in time sequence?
A. Run chart
B. Ishikawa diagram
C. Pareto chart
D. Histogram
Answer: A